25 August 2009

External colours and plastering

External painting was done last week - the feature colour didn't turn out as we expected but nevertheless it looks pretty cool.

External colours and plastering

16 August 2009

Internal walls

Things are definitely moving now - This week they have done the internal walls for the lower level.

Internal Walls - 15/08/2009

13 August 2009

Progress so far...

My apologies for not updating this blog for the past several months. I have been extremely busy and just haven't got around to keep this blog up to date.

After weeks of idling and a switchover to new site supervisor, things are finally moving with the house. Hopefully it will be completed before the end of the year.

Progress so far include:

- Roofing
- Rendering of external walls
- External painting of the upper level
- Plumbing
- Electrical wiring
- Network wiring
- Insulation
- Interior lining by the end of this week

Here are some photos showing the progress in the last several months:

Walls Rendering - 01/05/2009


Roof - 14/05/2009


Home - 21/06/2009


Home - 10/08/2009


New home - 13/08/2009